900 East Main Street, Suite 109

Grass Valley, CA 95945

530-648-4232

1250 East Ave #10

Chico, CA 95926

530-715-7184

Project Spotlight: Toro Creek Temporary Bridge

toro-creek-cover

A modular, rapid-deployment steel girder bridge designed to restore access over a storm-ravaged creek despite severe weight restrictions on the approach route.

 

The Challenge

  • The Problem: Heavy storm events washed out the road at Toro Creek. However, the only access route contained another bridge with a reduced load rating, preventing the contractor from hauling in heavy equipment or long-span pre-fabricated girders.
  • The Goal: Design a temporary crossing that could be built using only the equipment already on-site, while meeting HS20 vehicle loading requirements.

 

The Solution

  • Approach: We developed a modular 68′ single-span steel girder bridge designed for “on-site assembly.” By using shorter, 20′ W-beams connected with bolted splices, the contractor could transport materials past the restricted access bridge and assemble the spans in place.
  • Key Features: * Modular Splices: Bolted connections for ease of assembly/disassembly.
    • Foundation & Decking: Utilized “swamp mats” for the foundation and “crane mats” for the decking to simplify construction.
    • Rapid Retrieval: The design allows for quick removal if high waters return before the permanent bridge is completed.
    • Sustainability: All materials are fully reusable for future projects.
  • Tech/Tools Used: Structural Steel Design (AISC/AASHTO standards), HS20 Load Rating Analysis.

 

The Impact

  • Results: Successfully load-tested with a 38,000 lb grade-all. The bridge showed only 3/4″ of deflection, significantly better than the allowable limits.
  • The “So What”: This project showcases the ability to design around logistical “bottlenecks.” By tailoring the design to the contractor’s available equipment and the site’s physical constraints, we restored a vital traffic link that is currently serving the county during the permanent bridge’s design phase.

 

Lessons Learned

  • Logistics-Driven Design: This project reinforced that the best engineering solution isn’t just about structural integrity, but also about the “buildability” of the components within the specific logistical constraints of the site.

 

CONTACT US

Facebook
Twitter
LinkedIn
Pinterest